Planning fees for commercial and special buildings

Every commercial and special building type in the schedule, from shops and hotels to filling stations.

Commercial and special buildings cover a wide range, from shops and hotels to filling stations, masts and airports. Each type has its own rate, and some are charged by something other than building volume. The tables below list every type in the schedule.

Commercial and special buildings in 1st class urban areas

TypeRateMinimum rateAmendmentRevalidation
Warehouse₦400 per m³₦1,000,000₦84,000₦156,000
Hotel₦400 per m³₦1,500,000₦500,000₦500,000
Eatery₦400 per m³₦1,000,000₦500,000₦500,000
Industry (large scale)₦400 per m³₦1,500,000₦700,000₦700,000
Gas filling station₦450,000 per pump₦1,500,000₦1,000,000₦1,000,000
Town hall₦300 per m³₦375,000₦150,000₦156,000
Hostel₦300 per m³₦1,000,000₦1,000,000₦1,000,000
Park or golf course₦400 per m³₦1,500,000₦2,000,000₦2,000,000
Block of shops (1 to 5 shops)₦250 per m³₦307,800₦150,000₦150,000
Block of shops (above 5 shops)₦300 per m³₦600,000₦250,000₦250,000
Block of shops (two or more floors)₦400 per m³₦1,200,000₦500,000₦500,000
Mast₦2,000,000 (fixed)None listed₦500,000₦500,000
Airport₦1,000 × land areaNone listed₦2,000,000₦2,000,000
Airstrip₦1,000 × land areaNone listed₦2,000,000₦2,000,000
Jetty or container₦400 per m³None listed₦1,050,000₦1,050,000
Terminal₦400 per m³None listed₦1,050,000₦1,050,000
Bank₦400 per m³₦2,000,000₦600,000₦600,000
ATM₦400 per m³₦451,800Not listedNot listed
Church₦400 per m³₦417,600₦72,000₦180,000
Hospital₦200 per m³₦426,600₦72,000₦180,000
Private institution₦200 per m³₦407,700₦135,000₦210,000
Government building₦200 per m³₦453,600₦105,000₦210,000
Shopping office complex₦400 per m³₦1,200,000₦105,000₦420,000
Market₦400 per m³None listed₦315,000₦525,000
Petrol filling station₦350,000 per pump₦1,500,000₦600,000₦600,000
Lube bay₦350,000 per CM₦1,350,000₦320,000₦320,000
Piggery or poultry (livestock)₦350 per m³₦696,000₦100,000₦156,000
Sand mining site, retaining walls and structures at river bank₦400 per m³₦1,500,000₦500,000₦500,000
Signage and installation₦350,000 (fixed)None listedNot listedNot listed

Commercial and special buildings in 2nd class urban areas

TypeRateMinimum rateAmendmentRevalidation
Warehouse₦400 per m³₦1,000,000₦84,000₦156,000
Hotel₦400 per m³₦1,500,000₦500,000₦500,000
Eatery₦400 per m³₦1,000,000₦500,000₦500,000
Industry (small scale)₦300 per m³₦520,500₦54,600₦78,000
Petrol filling station₦450,000 per pump₦1,500,000₦1,000,000₦1,000,000
Gas plant₦450,000 per pump₦1,500,000₦1,000,000₦1,000,000
Town hall₦300 per m³₦375,000₦150,000₦156,000
Hostel₦300 per m³₦1,000,000₦1,000,000₦1,000,000
Park or golf course₦400 per m³₦1,500,000₦2,000,000₦2,000,000
Block of shops (1 to 5 shops)₦250 per m³₦307,800₦150,000₦150,000
Block of shops (above 5 shops)₦300 per m³₦600,000₦250,000₦250,000
Block of shops (two or more floors)₦400 per m³₦1,200,000Unclear in scheduleUnclear in schedule
Market₦300 per m³None listed₦210,000₦210,000
Mast₦2,000,000 (fixed)None listed₦500,000₦500,000
Airport₦1,000 × land areaNone listed₦2,000,000₦2,000,000
Airstrip₦1,000 × land areaNone listed₦2,000,000₦2,000,000
Jetty or container₦400 per m³None listed₦1,050,000₦1,050,000
Terminal₦400 per m³None listed₦1,050,000₦1,050,000
Bank₦400 per m³₦2,000,000₦600,000₦600,000
ATM₦400 per m³₦451,800Not listedNot listed
Lube bay₦350,000 per CM₦1,350,000₦320,000₦320,000
Hospital₦200 per m³₦426,600₦72,000₦180,000
Church₦400 per m³₦417,600₦72,000₦180,000
Private institution₦200 per m³₦407,700₦135,000₦210,000
Government building₦200 per m³₦453,600₦105,000₦210,000
Shopping office complex₦400 per m³₦1,200,000₦105,000₦420,000
Piggery or poultry (livestock)₦350 per m³₦696,000₦100,000₦156,000

Not everything is charged by volume

  • Filling stations are charged per pump.
  • Airports and airstrips are charged by multiplying the rate by the area of the land.
  • Masts and signage are fixed fees.

Worked example: a petrol filling station

A petrol filling station in a 1st class area is listed at ₦350,000 per pump, with a minimum rate of ₦1,500,000. With 4 pumps the calculation gives ₦1,400,000, which is below the minimum, so the fee is ₦1,500,000. With 6 pumps it gives ₦2,100,000, which is above the minimum, so the fee is ₦2,100,000.

Items to confirm with the planning office

A few entries in the schedule are unclear, and it is worth asking the office before you rely on the figure.

  • Market: the schedule states the rate "per block of building", so ask how several blocks are charged.
  • Lube bay: the rate is given "per CM", and the unit is not defined.
  • Airport and airstrip: the rate is multiplied by the land area, but the schedule does not state the unit.
  • Block of shops (two or more floors), 2nd class area: the amendment and revalidation fees are unclear in the schedule.

Choosing the right type

Pick the type that matches the main use of the building. A block of shops, for example, is listed three ways depending on the number of shops and floors: one to five shops, more than five shops, and two or more floors. If your building does not clearly fit one type, ask the office which entry applies.

Estimate your planning fee

Last reviewed: September 2026. Figures come from the Schedule of Planning Fees of the Ministry of Physical Planning and Urban Development, Awka. They are estimates, and the planning office confirms the final fee.